Installation Guide

Step 1 Clean

Sweep the base of the pothole of any loose debris by sweeping or raking. Ensure that no large loose rocks are present in the pothole before pothole repair step 2.  

 

Step 2  Pour

Fill the pothole with Go Green Cold Asphalt Patch. Recommended compacted depth is 25mm C 50mm. If area is deeper than 50mm, compact in layers (no deeper than 50mm per layer).

 

Step 3  Tamp

The best form of asphalt compaction is a vibrating plate compactor. Remember, the better the initial compaction, the sooner you will have total solidity. Pothole repairs, road reinstatements, asphalt overlays and driveway repairs that wont be subject to secondary compaction should receive additional compaction at the time of installation.  
 
 

 
 